Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
THE EDINBURGH SCHOOLS PARTNERSHIP LIMITED v GALLIFORD TRY CONSTRUCTION (UK) LIMITED [2017] ScotCS CSOH_133 (24 October 2017)
URL: http://www.bailii.org/scot/cases/ScotCS/2017/[2017]_CSOH_133.html
Cite as:
[2017] ScotCS CSOH_133
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
CA34/17
OUTER HOUSE, COURT OF SESSION
[2017] CSOH 133
OPINION OF LORD BANNATYNE
In the cause
THE EDINBURGH SCHOOLS PARTNERSHIP LIMITED
against
GALLIFORD TRY CONSTRUCTION (UK) LIMITED
Pursuer: Moynihan QC; MacRoberts LLP
Defender: Ellis QC; Burness Paull LLP
Pursuer
Defender
24 October 2017
Introduction
[1] In the present action the pursuer seeks to enforce the decision of an adjudicator
dated 28 March 2017.
The Issues
[2] The three broad issues discussed in the argument before me were these: whether the
adjudicator’s decision is invalid and ought to be set aside on the grounds that (1) he did not
have jurisdiction to reach his decision, (2) there was a procedural failure by the pursuer in
Page 2 ⇓
2
referring the adjudication to the adjudicator and (3) the decision he reached was in material
breach of natural justice?
Background
[3] In terms of a Project Agreement entered into between the pursuer and the City of
Edinburgh Council (“CEC”) dated 14 November 2001, the pursuer undertook to provide
certain services to CEC in respect of a number of schools in Edinburgh (“the project
schools”). Amongst services provided by the pursuer were (a) the design, construction and
refurbishment of the project schools (“the construction project”); and (b) the facilities
management of those schools (“the FM services”).
[4] For the purposes of the construction project, the project schools were divided into the
Stage 1 schools and the Stage 2 schools. In respect of the latter, in 2004 the pursuer entered
into a Design and Build Contract with the defender (“the D&B contract”).
[5] The pursuer in addition entered into an FM Agreement with Amey Community
Limited (“the FM Contractor”) for the provision of FM services by the latter to the pursuer
in connection with the Stage 1 and Stage 2 schools.
[6] The Stage 2 schools consisted of the following: Oxgangs Primary School; Firhill
High School; St Peter’s Primary School and Braidburn School.
[7] In January 2016, a gable wall at Oxgangs Primary School suffered a partial collapse
during a winter storm. The school was closed while immediate action was taken to render it
safe for occupation by schoolchildren and investigations were set in train in order to
discover the reasons for the collapse. Those investigations in turn expanded to cover the
other three schools which had been erected pursuant to the D&B contract as problems were
discovered firstly at Oxgangs, and then at each of the other three schools. Works of repair
Page 3 ⇓
3
were carried out by the defender on the express understanding that those works were being
carried out without any admission of legal liability.
[8] The work led to concerns about the construction of both Stage 1 and Stage 2 schools.
A dispute arose between the parties in relation to various matters arising from the foregoing
events. By adjudication notice dated 8 February 2017 the FM Contractor gave notice to the
pursuer of its intention to refer a dispute to an expert for adjudication (“the Related
Dispute”). In order to achieve a consistent determination of disputes, where any dispute
between the pursuer and the defender raises substantially the same issues as arise in an
adjudication between the pursuer and the FM Contractor, section 11 of the D&B contract
gives the pursuer the right to have the dispute between the pursuer and the defender
determined by the expert appointed in relation to the related dispute (that expert being
referred to in the D&B contract as “the Related Adjudicator”). The pursuer sought to
exercise that right in this case and served notice on the defender under paragraph 11.1 of
Schedule Part 2 of the D&B contact of its intention that the dispute between the parties be
referred to the Related Adjudicator. On 15 February 2017 both adjudications were
conjoined.
[9] The pursuer’s title to refer this matter to the related adjudicator was challenged by
the defender and the related adjudicator rejected this challenge setting out his reasons
therefor in a note dated 13 March 2017.
[10] Moreover the defender challenged the title of the related adjudicator to conjoin the
disputes on the basis that the pursuer had not served a preliminary statement and/or referral
notice. The adjudicator rejected this challenge setting forth his reasons therefor in a note
dated 13 March 2017.
Page 4 ⇓
4
[11] Lastly the defender challenged the entitlement of the related adjudicator to act in a
the related adjudication on the basis of purported bias on the part of the related adjudicator.
The adjudicator rejected this challenge setting out his reasons therefor in a note
dated 20 February 2017.
[12] On 28 March 2017 the adjudicator issued decisions in both adjudications.
The Submissions on behalf of the Defender
[13] As regards the first issue of jurisdiction, Mr Ellis advanced his argument in terms of
a number of separate chapters.
[14] The defender’s first argument was this: the pursuer had no title to commence an
adjudication for the sums claimed as the sums claimed were enforcement of rights which
arose under the D&B contract.
[15] The argument in support of the above contention can be summarised in this way: all
the pursuer’s rights under the D&B contract have been assigned. Title to commence
proceedings belongs to the assignee. As a result proceedings have to be commenced either
in the name of the assignee or by the assignee using the name of the pursuer.
[16] It was the position of Mr Ellis that it flowed from the assignation by the pursuer in
favour of the Governor and Company of the Bank of Scotland as Security Trustee (page 935
JB), that the pursuer assigned to the Security Trustee inter alia its whole right, title and
interest in and to all rights of the pursuer relative to the D&B contract. It was his positon
that in terms of Clause 2 of the assignation it was made clear that the assignation was to
have present and immediate effect. Mr Ellis accepted that throughout the assignation it was
said to be an assignation in security. However, critically it was his position that this made
no difference to the argument on title which he was advancing.
Page 5 ⇓
5
[17] Mr Ellis directed my attention to a Contract Direct Agreement (“CDA”) which was
entered into between inter alia the pursuer, the Bank of Scotland and the defender. It was
entered into at the same time as the assignation.
[18] Mr Ellis submitted that it was evident that the assignation was part of a larger suite
of documents intended to give effect to a commercial arrangement under which the pursuer
as a single purpose vehicle with no covenant of its own provided security to those investing
in the project. The real commercial interests being protected were those of the parties
behind the single purpose vehicle whose economic interests were in need of security. He
argued that there was no doubt that the parties intended that there be an immediate and
effective transfer of the relevant rights. The transfer of the rights was necessary in order for
there to be immediate security provided for those investing in the venture. As provided for
within the assignation itself, it is understood that the assignation was perfected by
intimation to the defender at the time.
[19] In development of his argument Mr Ellis turned to examine in a little detail the terms
of the assignation.
[20] Clause 1 of the assignation defines rights as follows:
“’Rights’ in relation to any contract, agreement or arrangement includes:
(a) the right to receive all and any monies payable thereunder;
(b) the proceeds of any payment thereunder;
(c) all claims for damages for any breach thereof (except for a breach by the
Assignor);
(d) the benefit of all warranties and indemnities contained therein;
(e) any right to terminate or rescind the same; and
(f) any right to perform and observe the provisions of the same and to compel
the performance and observance of same.”
Page 6 ⇓
6
[21] Mr Ellis made the short point that the definition of rights was very wide and clearly
includes claims of a type dealt with in the adjudication.
[22] Clause 2 is in the following terms:
“ASSIGNATION IN SECURITY
In security of the payment and discharge of the Secured Finance Liabilities the
Assignor herby assigns to the Security Trustee its whole right, title, interest and
benefit in and to:
(a) the Project Documents; and
(b) all Rights of the Assignor relative to the Project Documents.”
[23] The above clause Mr Ellis submitted is the operative part of the assignation and
amounts to an immediate assignation of everything in the D&B contract.
[24] Clause 3 contains the intimation provisions and in particular Clause 3.1(a) provides:
“The Assignor shall:
(a) procure that on execution of this Deed notice of the assignation of the Project
Documents pursuant to this Deed (in the form of the notice set out in Part 2 of
the Schedule) or in such other form acceptable to the Security Trustee is given
to all such persons to whom such notice is required to be given in order to
create a valid fixed security over the Assigned Rights under the law of
Scotland; and ...”
[25] On execution the deed is to be intimated. This shows the clear and present intention
that the immediate transfer of rights should take place. It confirms the terms of Clause 2.
[26] He then moved to Clause 4.3 which provides:
“The Assignor shall:
(a) procure the due and punctual performance by each of the other parties to the
Project Documents of their respective obligations thereunder; and
(b)
Page 7 ⇓
7
(i) perform the obligations on its part contained in the Project
Documents;
(ii) notify the Security Trustee of any default (whether by it or by any
other party) under the Project Documents promptly after becoming
aware of it; and
(iii) institute and maintain all such proceedings and take such other steps
as may be necessary or expedient (in the sole opinion of the Security
Trustee) to preserve or protect the interests of the Assignor and of the
Security Trustee in and to the Project Documents.”
[27] It was Mr Ellis’ position that on a sound construction this clause operates to do the
following: to give to the pursuer the duty to manage rights it has transferred to the Security
Trustee; what it does not do is give the pursuer formal title to these rights and thus formal
title to institute proceedings. This construction of clause 4.3 he submitted fitted in with the
traditional analysis of an assignation. What we have here is an immediate transfer of rights
from the cedent to the assignee. However, the cedent is to manage these rights.
[28] Further confirmation of this immediate transfer is given by the terms of Clause 4.4
which provides:
“The Assignor shall not without the prior consent in writing of the Security Trustee
(not to be unreasonably withheld):
(a) assign, transfer or otherwise dispose of or create or incur or knowingly
permit to subsist any security or encumbrance over any of the Assigned
Rights other than as expressly permitted in the Common Terms Agreement;
(b) waive, fail or delay to enforce any of its rights under the Project Documents
or terminate or agree to terminate the Project Documents or any of them other
than as expressly permitted in the Common Terms Agreement; or
(c) take or omit to take any action the taking or omission of which could
reasonably be expected to result in the alteration or impairment of the Project
Documents or this Deed or any of the rights under the Project Documents.”
[29] The pursuer by this clause is obliged to take certain steps, however, limitations are
placed on this.
[30] Clause 4.6 then provides:
Page 8 ⇓
8
“Without prejudice to Clause 4.5 (Liability of Assignor), if the Assignor fails to perform
any of its obligations under the Project Documents, the Security Trustee may, but
shall not be under any obligation to, perform or procure the performance of such
obligation. If the Security Trustee shall perform or procure the performance of any
obligation of the Assignor under the Project Documents, the Assignor shall, without
prejudice to any other right of the Security Trustee, forthwith on demand by the
Security Trustee reimburse the Security Trustee for all reasonable costs and expenses
properly incurred by it in so doing together with interest thereon at the Default Rate
from the date of demand until the date of payment by the Assignor to the Security
Trustee (but without double counting of interest which is payable as such costs and
expenses under any other Senior Lender Finance Document).”
[31] Mr Ellis took from the above provision that the Security Trustee is entitled to step in
and perform the obligations incumbent on the pursuer and this shows that there has been an
effective transfer of rights to the Security Trustee.
[32] He went on to submit that a further confirmation of the creation of an immediate
transfer of rights can be seen from the terms of Clauses 10.1 and 10.2 of the assignation.
[33] He submitted that the immediate transfer of rights was important to the Security
Trustee where there was competition with any other creditor. If there was not an immediate
transfer then the Security Trustee would not win the competition with the other creditor.
[34] In respect to the CDA (page 710 JB) Mr Ellis directed my attention to Clauses 3.1
and 3.2 which provide:
“3.1 The Global Agent hereby gives, and the Contractor and Guarantor
acknowledge, notice to the Contractor and Guarantor that the Service
Company has granted or, as the case may be, is to grant with effect from the
Effective Date, Security over, inter alia, the Secured Agreements under the
Security Documents in favour of the Security Trustee (including an
assignation by way of security of the Service Company's present and future
rights, title, benefit and interest in and to the Secured Agreements)
("Assigned Rights"), and the Contractor and Guarantor consent to the
creation of the Security over the Secured Agreements on the terms set out in
the Security Documents.
3.2 The Service Company hereby gives, and the Contractor and Guarantor
acknowledge, notice to the Contractor and Guarantor that the Security
Trustee has agreed with the Service Company that, until such time as the
Page 9 ⇓
9
Security Trustee notifies the Contractor and Guarantor in writing to the
contrary, the Service Company may exercise all of the Assigned Rights save
that the Service Company may not without the prior written consent of the
Global Agent amend, waive or modify, cancel, terminate, suspend, surrender,
assign, novate or transfer any of the Secured Agreements or the Assigned
Rights.”
[35] In these clauses where the Contractor is referred to, this is the defender and the
pursuer is the Service Company.
[36] What Mr Ellis took from Clause 3.1 was this: it is once again clear that what is
intended is not a future security but one created with immediate effect.
[37] As regards Clause 3.2 it reflects what is to happen in terms of the assignation: the
pursuer is entitled to exercise certain rights but subject to limitations. He argued that in
terms of Clause 3.2 of the CSA (as in the assignation) the right to manage is given to the
pursuer. This construction was consistent with an immediate transfer of rights.
[38] Having analysed these documents the conclusion Mr Ellis invited the court to draw
from them was this: in order for an effective security to be created it has to transfer the
rights in terms of the D&B contract immediately. The pursuer can exercise (manage) those
rights but does not have title to those rights and is not the owner of the rights. The terms of
those documents on a proper construction were consistent with the argument on title which
he was advancing.
[39] Mr Ellis’ argument continued: it flowed from the above that the pursuer did not
have title to the claims which were made within the adjudication. Without title to the claims
which were made within the adjudication the pursuer could not commence an effective
adjudication. Title is a jurisdictional issue which affects the validity of an adjudication (see:
Rok Build Ltd v Harris Wharf Development Co Ltd [2006] EWHC 5573 (TCC) at paragraph 19
and Mailbox (Birmingham) Ltd v Galliford Try Construction Ltd [2017] BLR 180).
Page 10 ⇓
10
[40] Mr Ellis then proceeded to address me as to the nature of an assignation: an
assignation is the means of transferring the title to incorporeal moveable rights. Once the
assignation is perfected by intimation the right is vested in the assignee (see: Stair Memorial
Encyclopaedia Vol 18 paragraphs 16 and 656). In order for there to be an effective assignation
in Scots Law there requires to be an immediate transfer of rights, see: Carter v McIntosh
[1862] 24D 925 at 933; Gallemos L:td (in receivership) Ltd v Barratt Falkirk Ltd 1989 SC 239
[41] He in particular directed my attention to the discussion in Gallemos v Barratt Falkirk.
This he submitted was of significance given that the assignation in question was an
assignation in security.
[42] He took me first to the Opinion of Lord Dunpark at page 242 who described what
was necessary for an effective assignation:
“In my opinion an effectual assignation must contain words which may be construed
as effecting an immediate transference of A’s right against C (A’s debtor) to B (the
assignee), and the transfer is completed when intimation of the transfer is made to C,
who then knows that B has become his creditor in place of A;”
[43] He also drew the court’s attention to the Opinion of Lord Cowie at page 246 who
having considered the Opinion of Lord Justice Clerk Inglis in Carter v McIntosh derives the
following from it:
“Accordingly it appears that all that is required to constitute an assignation are, first,
words giving authority or directions which if fairly carried out will operate a
transference, and secondly, that there must be a present intention to transfer.”
[44] That these are the requirements for constituting an assignation is further confirmed
by the Lord Justice Clerk in McCutcheon v McWilliam 1876 3R 565 where he sates at page 571:
“Any words which express a present intention to transfer are sufficient as an
assignation.”
Page 11 ⇓
11
[45] The analysis in Gallemos v Barratt Falkirk is confirmed in Jack v Jack at paragraph 36.
However, it does not add anything to what is said in Gallemos v Barratt Falkirk.
[46] So, if assignation in the instant case is to be effective it must have immediately
transferred rights to the Security Trustee. The court should be very slow to hold that it had
not transferred rights and thus the assignation could be rendered ineffectual.
[47] His argument continued in this way: from the foregoing analysis there is no doubt
that following the assignation and intimation thereof in the present case title for the rights
arising under the contract belonged to the security trustee.
[48] An assignation strips the cedent of title to claims and to bring an action based on
those claims. If there is no title the action is a nullity: Bentley v MacFarlane 1964 SC 76 at 79
and 80.
[49] In Bentley v MacFarlane the facts in so far as material are set out in the rubric:
“A motorist who was involved in a collision with another car assigned his right of
action arising out of the collision to a third party. He subsequently raised an action
of damages against the driver of the other car, who pleaded no title to sue.”
[50] Mr Ellis directed my attention to the Opinion of the Lord President at page 80 where
he opined that the pursuer had no title to sue and observes that:
“He (the pursuer) had assigned any title he had to Mr B. Nothing that Mr B
subsequently did by reassignation, which only operated from its own date, affected
the positon at the date of raising an action. And nothing Mr B subsequently did gave
the pursuer as at the date of the raising of the action any title to initiate proceedings.
At the best for the pursuer Mr Brown only gave him a title to sue in December 1961,
long after the action was raised and from the time when the action was raised until at
least December 1961, the pursuer had not the vestige of a title at all.
The pursuer founded upon a passage in Maclaren on Court of Session Practice at
page 219, which is in the following terms: ‘A party who has granted an assignation
and then raises an action has a good title to carry it on if he obtains a retrocession
Page 12 ⇓
12
pendente processu.’ This passage in my opinion, is not sound law, and I agree with
Lord Strachan’s observations upon it.”
[51] Thus in the instant case the pursuer had no title, he had certain personal rights but
no title.
[52] Mr Ellis went on to contend that the law of Scotland recognises both real rights and
personal rights. It recognises no intermediate rights. A critical feature of Scots Law is that a
party either has a title to a right or it does not. There is no intermediate positon. In support
of that contention he directed the courts attention to Burnett’s Trustees v Grainger 2004
SC(HL) 19 at paragraphs 18, 19, 46, 87 and 88 and; Royal Insurance (UK) Ltd v Amec
Construction Scotland Ltd 2008 SC 2001 at paragraph 15.
[53] Having examined in some detail first the material provisions of the documentation
and second the general law, with respect to assignation Mr Ellis then moved to consider
what he described as the central question in the instant case: whether the fact that the
assignation is in security affects the divestiture of the cedent and the transfer of the title to
the assignee? His answer to that question was; there is no reason in principle why it should.
[54] In elaboration of this answer he submitted: principle indicates that the very nature
of an assignation is that it is a transfer of the right. Any decision to the effect that an
assignation in security did not affect the transfer of the right in the generality of cases would
be to deny an assignation in security its very nature as an assignation. Such a step would
also be undesirable in practice as it would mean that the debtor would have to deal with
two parties in any transaction with his debt. What would happen if the two parties
disagreed? Since an assignation by its very nature is an immediate transfer of the right it is
submitted that only the assignee can have title to the right. There is no reason in principle or
practice that this basic analysis does not apply to an assignation for the purposes of security
Page 13 ⇓
13
as well as to an assignation in perpetuity. He submitted that there is no authority which
states that this basic analysis does not apply to an assignation for the purposes of security.
The simple and straightforward application of the principle of a transfer of the right protects
the debtor. What is important from the debtor’s point of view is who has title to the debt.
The debtor needs to know who the title belongs to. The debtor cannot be expected to
enquire into the nature of the relationship or the state of indebtedness between the cedent
and the assignee. There is no justification in general to treat an assignation in security any
differently from an assignation for any other purpose in this regard.
[55] Mr Ellis referred me to Gloag and Irvine, Law of Rights in Security at page 478 where
the following is said:
“In addition to interrupting the bona fides of the debtor, intimation has the effect of,
and is necessary for, thoroughly divesting the cedent. No one can be fully divested
of a debt till another has been invested therein; and, accordingly, the cedent is not
wholly divested till, by intimation, the assignee has become the creditor and is fully
vested in the debt. Similarly, intimation to the debtor, and that alone, effectually
excludes claims by third parties ; for such claims can be derived only from and
through the cedent; and, as all right in the cedent is evacuated by intimation, claims
by third parties derived from him are, after intimation, necessarily excluded. Hence
the effect of intimation is to perfect the title of the assignee, not only against the
debtor but also against the cedent and third parties claiming rights through him.“
[56] Mr Ellis emphasised that the context of the above discussion was the law of rights in
security.
[57] Mr Ellis then turned to examine two passages which he understood would be relied
upon by the pursuer with respect to this issue:
First, Maclaren Court of Session Practice at page 219:
“The assignation of a claim in security of a debt due to the assignee does not
preclude the cedent from suing for the claim, so long as there is a surplus for which
the assignee must account, or so long as the assignee does not object. Where,
however, the true interest lies with the assignee and not with the cedent, the latter
Page 14 ⇓
14
will only be allowed to proceed in an action provided he finds caution for the
expenses of process, or sists the assignee as dominus litus.”
And secondly, McBryde The Law of Contract in Scotland paragraph 12-79 where the author
says, inter alia:
“Once an assignation is intimated to the debtor, the cedent, prima facie, no longer has
a title to sue the debtor. An assignation might not completely divest the cedent. It
could be in security, leaving the cedent with the right of reversion or only part of a
debt may be assigned. The result is that the cedent may retain a title to sue.”
[58] Each passage was said to be supported by reference to three authorities, namely:
Robertson Co v Exley, Dimsdale & Co 1832 11 S 91; Fraser v Duguid 1838 16 S 1130 and;
Manson v Baillie 1850 12 D 775.
[59] It was Mr Ellis’ positon that the three cases cited do not support the propositions
contained in the above passages.
[60] Mr Ellis analysed each of these cases in turn:
[61] First with respect to Robertson & Co v Exley, Dimsdale & Co he submitted that the
assignation appeared to be of sums due after a current account balance was struck. The
court allowed the cedent to bring proceedings to elucidate what was the correct balance.
The interlocutor in the case is expressed as doing so on the basis that the assignation was
“not to the ground of action, but is merely of the balance in security”. It was his positon that
the case might be most clearly seen as an example of a partial assignation. The decision was
not based on the cedent retaining title in an assignation in security. It did not support the
pursuer in the present case having a title to sue.
[62] Secondly, Fraser v Duguid he submitted again seemed to have been a case of a partial
assignation. In any event the main decision of the court was to confirm that an assignee may
Page 15 ⇓
15
sue in the name of the cedent. There was nothing in that case which affected the general
principle as to what was an assignation.
[63] Thirdly as regards Manson v Baillie it was not a decision about who had title to raise
the action. It was a decision of application to very special circumstances in which the right
which had been assigned was to be abandoned by the assignee and the cedent’s right to be
revived. The revival might perhaps only be applicable to a situation where the cedent’s
interest extended well beyond the amount of the obligation secured by the assignation. The
radical right recognised appears similar to the radical right that is recognised in bankruptcy,
if a trustee abandons an asset which would not allow the bankrupt to prosecute the claim
before the trustee abandons it: cf Geddes v Barry 1822 1 S 480.
[64] Mr Ellis emphasised the very special and unusual circumstances in which it was held
that there was title to sue. However, he did accept that it was an exception to the clear rule.
The circumstances in which title was said to arise were such that no assistance was provided
by the case to the pursuer’s argument in the present action.
[65] In conclusion he submitted this regarding these cases: they do not suggest that as a
matter of principle an assignation in security is to be treated differently as to its effect on
divestiture of title from an assignation for other reasons. It was his positon that the
circumstances of the three cases were very clearly distinguishable from the present. Not
least because that as in the present case there is no suggestion within the documentation that
the assignation in security is merely a partial assignation. None of these cases was of
assistance to the pursuer.
[66] Mr Ellis then addressed the question of the significance regarding the title of the
pursuer of the CDA. He noted that the pursuer relies upon this document and in particular
Page 16 ⇓
16
the pursuer seeks to rely on the terms of Clauses 3.1 and 3.2 which are in the following
terms:
“3.1 The Global Agent hereby gives, and the Contractor and Guarantor
acknowledge, notice to the Contractor and Guarantor that the Service
Company has granted or, as the case may be, is to grant with effect from the
Effective Date, Security over inter alia the Secured Agreements under the
Security Documents in favour of the Security Trustee (including an
assignation by way of security of the Service Company’s present and future
rights, title, benefit and interest in and to the Secured Agreements)
(‘Assigned Rights’), and the Contractor and Guarantor consent to the
creation of the Security over the Secured Agreements on the terms set out in
the Security Documents.
3.2 The Service Company hereby gives, and the Contractor and Guarantor
acknowledge, notice to the Contractor and Guarantor that the Security
Trustee has agreed with the Service Company that, until such time as the
Security Trustee notifies the Contractor and Guarantor in writing to the
contrary, the Service Company may exercise all of the Assigned Rights save
that the Service Company may not without the prior written consent of the
Global Agent amend, waive or modify, cancel, terminate, suspend, surrender,
assign, novate or transfer any of the Secured Agreements or the Assigned
Rights.”
[67] It was his position that it was clear from the foregoing that immediate transfer of the
rights is intended. The question is: what is the effect of allowing the service company (the
pursuer) to “exercise” the rights. The pursuer contends that as a result of this it is entitled to
advance the claims which have been assigned. His positon was that this simply could not be
correct. To give effect to that argument would mean that the rights to the claims have not
been assigned but that they remain with the cedent. There would have been no transfer.
There was, on this hypothesis, no assignation at the effective date. Rather the rights
remained with the pursuer. Such a position clearly could not be an effective assignation
according to the cases of Gallemos and Jack. What is more in these circumstances the rights
would not have been transferred to the security trustee and would have remained
susceptible to the pursuer’s creditors. No security would have been granted. It is clear that
Page 17 ⇓
17
the parties intended to create an effective assignation but thereafter to make provision in
respect of the management of those rights. The pursuer’s interpretation would lead to that
assignation and security being ineffective. It was his positon that it would not be
appropriate to adopt an interpretation which frustrated the objectives of the contract see:
Chitty on Contracts 32nd Edition paragraph 13 – 084.
[68] He argued that the most sensible content is given to these provisions if they are
understood not as leaving title with the pursuer but with leaving management of the rights
thus allowing it to pursue claims and to give good discharges therefore but always on behalf
of the security trustee. Any proceedings would require to be raised in the name of the
security trustee who has title to the claims. He submitted that this is a perfectly reasonable
and workable construction which is consistent with there being an effective transfer of the
rights and security to the security trustee but with the pursuer managing those rights on a
day to day basis until it is in default. Thus effectively the debtor knows that he can deal
with the pursuer on behalf of the security trustee. Nonetheless title remains with the
Security Trustee. Any proceedings to enforce the claim therefore must be raised in the name
of the person who has title, namely: the Security Trustee.
Conclusion
[69] It was Mr Ellis’s positon that the consequence of the foregoing is that the pursuer has
no title to bring proceedings. The proceedings ought to have been commenced in the name
of the Security Trustee or be raised by the Security Trustee in the name of the pursuer. It is
not suggested on behalf of the pursuer that the adjudication or indeed the current court
proceedings are brought by the Security Trustee using the name of the cedent. The pursuer
had no title at the time of the notice of adjudication commencing the adjudication
Page 18 ⇓
18
proceedings. In these circumstances the court should uphold his first argument in respect to
the validity of the adjudication.
The Second Issue
[70] The second argument was based on an alleged failure by the pursuer to follow the
procedural requirements of the D&B contract. The argument continued that due to this
failure the adjudicator did not have jurisdiction to hear the adjudication. In particular it was
contended that there was an omission to provide a statement of particulars as required in
terms of paragraphs 11.2 and 11.3 of the Schedule Part 2 of the D&B contract.
[71] Paragraphs 11.2 and 3 provide as follows:
“11.2
In the event that the Employer notifies the Contractor and the other party to
the Related Dispute in writing of its intention that the Dispute be referred to
the adjudication of the Related Adjudicator, then the Employer will provide
no later than seven (7) days from the date on which the Related Referring
Party gave notice of its intention to refer the Related Dispute to adjudication,
to the Related Adjudicator and to the other parties to the Dispute and Related
Dispute the particulars set out in paragraph 11.3.
11.3 The particulars referred to in paragraph 11.2 are;
(a) a copy of this Agreement (to the Related Adjudicator only);
(b) a copy of the Adjudication Notice referred to in paragraph 2.1;
(c) a preliminary statement from the Employer setting out
(i) the basis and grounds for consolidation of the Dispute
and the Related Dispute;
(ii) the cases of the parties to the Dispute (Insofar as the
cases of both parties to the Dispute can at the relevant
time be described);
(iii) any relief sought by the parties to the Dispute; and
(iv) a list of and copies of any documents served in relation
to the Dispute.
Page 19 ⇓
19
Any such particulars sent by the Employer to the Related-Adjudicator
shall be sent at the same time to the other parties to the Dispute and
the Related Dispute.”
[72] Thus 11.2 required a statement of particulars containing information as listed in
paragraph 11.3. Only after service of these particulars may the related adjudicator give
notice of his intention that the dispute and related dispute be conjoined. That notice of
intention by the Related Adjudicator must be given within 7 days of the date when the
Related Referring Party (here the FM Contractor [Amey]) gave notice of its intention to refer
the related dispute to adjudication. Amey gave such a notice of intention on 8 February
2017. The pursuer gave the defender notice of intention to refer the dispute to adjudication
on 13 February 2017. On 14 February 2017 the pursuer sent the related adjudicator a letter.
That letter is relied upon by the pursuer to demonstrate the fulfilment of the obligations
incumbent on it under paragraphs 11.2 and 11.3 of the Schedule Part 2.
[73] In the instant case the failure in said letter was this: the letter did not set out the
matters detailed in 11.3. In particular all that is said in relation to the matters in 11.3(c)(i)
and (ii) was by reference to certain parts of the adjudication notice and recording that the
defender had denied liability.
[74] Mr Ellis sought to put this failure within the statutory framework for adjudications
as provided by section 108(2) of the Housing Grants Construction and Regeneration
Act 1996. It requires the contract to inter alia provide a timetable with the object of securing
the appointment of the adjudicator and referral of the dispute to the adjudicator within
7 days of the notice of adjudication in the dispute. If the contract does not provide this then
the scheme under the Construction Contracts (Scotland) Act will apply. The notice under
section 11.2 is the means by which the dispute is in the present case referred to the
Page 20 ⇓
20
adjudicator as confirmed by paragraphs 11.6 and 11.7. It is the means by which the contract
complies with the requirements of the Act.
[75] Thus the particulars under 11.3 serve the purpose of referring a dispute which is to
be conjoined to the adjudicator. Accordingly it forms the equivalent of a referral notice
under the scheme. The particulars are therefore intended to provide the referral of the
dispute to the related adjudicator. Given the foregoing it is an important document. The
requirements in the contact need to be fully complied with. Notice is given both to the
adjudicator and to the responding party of the details of the dispute. Mr Ellis’ argument
continued as follows: given that background it is not sufficient simply to refer to the
adjudication notice. The required details must be set out within the referring document
itself. In the present case the letter itself does not set out the details of the dispute. It simply
refers to paragraphs within the adjudication notice. It does not contain the detail, so far as
the cases of both parties can at the time be described. It did no more than record that the
defenders denied liability. The notice accordingly did not conform to the requirements of
paragraph 11.3. Thus there was no valid conjoined adjudication.
[76] The above concluded the first branch of the defender’s argument relative to
jurisdiction.
The Third Issue
[77] In terms of the next branch of the defender’s argument Mr Ellis contended that there
had been a number of material breaches of natural justice.
[78] The defender’s first contention was of apparent bias on the part of the adjudicator.
[79] The legal framework within which that argument fell to be considered was not a
matter of dispute between the parties. The correct test is that stated by Lord Hope in Porter
Page 21 ⇓
21
v Magill [2002] 2 AC 357 that “a fair minded and informed observer” would conclude that
there was “a real possibility of bias”.
[80] The factual basis upon which Mr Ellis advanced the above argument was this: the
adjudicator had decided in an adjudication between the pursuer and Amey on 11 November
2016. In the course of doing so the adjudicator interpreted parts of a contract in substantially
the same terms as the D&B contract with which the present dispute is concerned. That
earlier adjudication related to Stage 1 schools for which a D&B contract had been concluded
in 2001. There was a determination that defects existed in similar buildings in Stage 1
schools using the same construction techniques used in Stage 2 schools. In the course of his
decision in the adjudication which is the subject of this case the adjudicator referred to his
earlier conclusions on parts of the contract. This it was submitted showed that he had
approached the current adjudication with that earlier decision in mind. There was
accordingly a real possibility of bias.
[81] The next section of the argument in terms of this chapter of breach of natural justice
was this: the adjudicator had not allowed the defender a response to matters raised in a
reply dated 10 March 2017 made by the pursuer to certain objections on jurisdictional
grounds which had been advanced by the defender. It was argued that this amounted to a
breach of natural justice.
[82] The factual circumstances founding this contention were that the no title issue was
first raised before the adjudicator by the defender in a response document of 3 March. That
point was responded to by the pursuer in a document of 10 March 2017. In addition on
10 March the pursuer produced a letter of consent and a number of authorities were referred
to on the no title issue. It was this to which the defender had not been given an opportunity
by the adjudicator to respond.
Page 22 ⇓
22
[83] It was argued by Mr Ellis that this failure to allow a response was a material one in
that the response might have made a considerable difference to the adjudicator’s
determination. The issue of no title is an important one and potentially determinative of the
dispute. A material breach on a matter which is of importance may invalidate an
adjudicator’s decision, see: Cantillon Ltd v Urvasco Ltd [2008] BLR 250 at paragraphs 56
and 57.
[84] Mr Ellis also advanced as part of his argument regarding a failure to allow a
response that in addition to failing to allow the defender an opportunity to respond to the
line of authority put forward by the pursuer, the adjudicator had referred to a further
authority of his own on the application of which he invited no comment. It was argued that
the further authority of his own demonstrated that the adjudicator had not fully understood
what the arguments for the defender would have been. This procedure was unfair. Mr Ellis
accepted that the foregoing point as a standalone one would not amount to a material breach
of natural justice, however, it could be considered in terms of the argument regarding a
failure to allow the defender to respond.
[85] The third argument was that the adjudicator referred to his earlier adjudication
decision and his reasoning therein. The assumption is that it was necessary for him to do so
in order to reach his conclusions. Again, he had not made it apparent to the parties in the
current adjudication that he intended in any way to rely on his earlier decision. Thus no
opportunity was offered to the parties to comment on that earlier decision. This once more
amounted to a denial of natural justice.
[86] For the foregoing reasons Mr Ellis moved that I should sustain the second
plea-in-law on behalf of the defender and set aside the adjudicator’s decision. This would in
Page 23 ⇓
23
consequence require me to sustain the defender’s third and fourth pleas-in-law and to
assoilzie the defender .
The Reply on behalf of the Pursuer
Title to Sue
[87] In response to the position advanced by Mr Ellis, Mr Moynihan argued as follows.
[88] There is a valid, present assignation of the D&B contract, but it is an assignation in
security. The difference between an assignation in security and an absolute assignation is a
significant one for the purposes of the argument on title to sue. It was a difference which the
defender failed to recognise in the argument put forward by Mr Ellis. Contrary to the
suggestion in the pleadings of the defender and as set forth by Mr Ellis in his submissions in
an assignation in security, the cedent is not stripped of title. Such an assignation does not
deprive the cedent of ownership of the contractual rights.
[89] In support of this contention Mr Moynihan first directed my attention to: Halliday
Conveyancing Law & Practice at paragraph 8.71 where the author explains in a section headed
“Assignations of Incorporeal Rights in Security” as follows:
“Incorporeal rights which are assignable may normally be made the subject of
security. The documentation may be either expressly as security for a personal
obligation or by way of ex facie absolute assignation or transfer qualified by a
separate document to the effect that the transaction is truly one which creates a
security. The forms of assignation or transfer are appropriate to the nature of the
right assigned and the creditor’s title should be completed by intimation or notice as
in the case of an absolute assignation or transfer. An assignation or transfer in
security does not in a question between the debtor and the creditor divest the former
or ownership of the security subject, and it is the duty of the creditor, subject to the
terms of the relevant documents, to consult the debtor in any dealings with it.
Accordingly it is necessary to incorporate in the documents any powers of dealing
with the security subject which the creditor considers he may require.”
Page 24 ⇓
24
[90] Mr Moynihan also relied on the passage in Maclaren, Court of Session Practice at
page 219, which I have earlier set out in full, with particular reference to the implications for
title to sue where an assignation is in security.
[91] Lastly he turned to McBryde: The Law of Contract in Scotland at paragraph 12-79
which I set out in full earlier and commented on that passage as follows:
It correctly recognises the conceptual distinction between an absolute assignation and an
assignation in security and the consequence of that distinction for the cedent's title to sue in
respect of the rights assigned in security. The authorities cited at footnote 258 support the
proposition that an assignation in security might not completely divest the cedent, with the
result that the cedent may retain a title to sue: Robertson & Co v Exley, Dimsdale & Co (1832)
11 S. 91; Fraser v Duguid (1838) 16 S. 1130; and Manson v Baillie (1850) 12 D. 775. The last of
these provides the clearest authority. The pursuer, Manson, assigned a debt which he
claimed was due to him by trustees of his late uncle's estate, to another individual, Cullen, in
security of advances made by Cullen to him. The operative provision in the assignation
read:
“... surrogating hereby, and substituting the said John Cullen, and his foresaids, in
my full right and place of the premises, with full power to them to ask, crave, uplift,
and pursue for the sums of money, principal, interest, and factor's fee hereby
assigned. ...”
Cullen raised an action in his own name against the trustees, which failed. He declined to
proceed further with the case. Manson petitioned the House of Lords, stating that the
assignation “was merely in security of certain advances” and that “the radical and real right
and interest in the said action and claims, remain in your petitioner”. The matter was
remitted to the Court of Session with instructions to consider whether Manson had such title
and interest in the action as to entitle him to be sisted as a party. As the report narrates, the
Page 25 ⇓
25
trustees advanced the same line of argument as the defender does here: although the
assignation bore to be only in security, it conveyed the debt to Cullen, with full powers to do
everything which the cedent would do himself. The trustees submitted that “till [Manson]
has retrocessed, he was not entitled to appear in the action”. The Court held that Manson
had title and interest in the action, and although the report would suggest that the focus was
primarily on Manson's interest (Cullen was obliged to account to him for any balance once
his debt was satisfied) the 'no title argument', based upon an assignation in security
containing similar operative wording, was explicitly before the Court and was rejected.
The defender's argument is substantially founded on the assignee being the party that has
the sole financial interest in the D&B contract. That argument is wrong. The security
trustees (the assignees) do not have the sole financial interest in the contract. Rather the
pursuer continues to have a material interest in the D&B contract.
[92] Mr Moynihan sought support for the foregoing in the terms of the assignation and
surrounding documents.
[93] He firstly submitted that the pursuer has a reversionary interest: (Assignation
Clause 16). Secondly the pursuer has a present and continuing financial interest in the
contract for these reasons: (i) the pursuer remains liable to perform all of the obligations
under the contract see: the Assignation Clause 4.3(b)(i), the Intimation and CDA
Clause 4.5.3 - no Additional Party has any obligation, and (ii) payments by the defenders are
made to the pursuer's bank account (CDA clause 5.1, JB 719) Beyond that any sum
recovered by the pursuer from the defender in respect of the present claim would be
payable to the pursuer: CDA Clause 5.1.
Page 26 ⇓
26
[94] The defender accepts that the authorities in Maclaren as referred to above support the
conclusion that the cedent in an assignation in security may retain title to sue at least in
exceptional circumstances.
[95] That must include the present case where:
(a) the pursuer has a present financial interest in the claim as explained above.
(b) there is an agreement among the security trustees, as assignee, the pursuer, as
cedent, and the defender, as debtor, that the pursuer may exercise the rights
prior to any Enforcement Event. This submission was made under reference
to the Assignation, Clauses 4.3(b)(iii) and contrast Clause 5(d), the Intimation;
and CDA Clause 3.2; and
(c) the assignee has given its consent to the pursuer proceeding with the
adjudication. The fact that this came later on the same day after the
adjudication notice had been served is irrelevant because as in Manson v
Baillie what is relevant was that Cullen (as assignee) asserted no objection
when asked by the Court.
[96] With respect to the defender’s construction of Clause 3.2 of the CDA he submitted
that it was too narrow, in so far as Mr Ellis argued that it did not leave the title with the
pursuer but merely management of the rights. Properly construed that clause means that
the pursuer retains title to sue for its own interest, that he submitted was the positon for the
following reasons:
(a) That it is consistent with the terms of the Assignation, Clause 4.3(b)(iii), in
particular when that clause is contrasted with Clause 5(d) which confers on
the assignee the right to commence legal proceedings only from the date of an
Enforcement Event.
Page 27 ⇓
27
(b) There is no surprise in any of this. The parties are merely taking advantage of
the “exception” which has been recognised by Mr Ellis in the course of his
address to the court in circumstances in which it is clear that the assignee
wishes to undertake no additional liability save when directly necessary to
protect the secured creditors should an Enforcement Event occur.
[97] None of the foregoing prevents the assignation in security in a competition between
creditors being as valid and effectual as an absolute assignation. The proper conclusion here
is that the pursuer had title to sue this adjudication.
The Response to the Pursuer’s Contention that there had been a Failure to Follow the
Procedural Requirements of the D&B Contract
[98] In regard to the contention that there was a defect in the statement of particulars
Mr Moynihan referred me to Clause 11.3 of the D&B contract which set out the particulars
that were to be contained in the statement.
[99] He began his submission by referring me to 11.3(c)(iv). He described this as an
interesting provision. He observed that a number of documents were set out as being
required to be produced in order to conform with 11.3. What was noteworthy was they
could just be attached. There was no requirement for them to be repeated ad longum in the
statement of particulars. There was nothing there which suggested that if one can find the
information required in terms of 11.3 in some other document referred to within the
statement of particulars that this amounted to non-compliance with the terms of the
provisions.
[100] Mr Moynihan then directed my attention to the letter relied upon by the pursuer as
showing that the requirements of 11.2 and 11.3 were met (the letter of 14 February 2017
Page 28 ⇓
28
JB 219) and drew my attention to the fact that there was provided with it a copy of the
adjudication notice. This document set out at some length the nature of the dispute. He
then asked the question: what would be gained in repeating that at length in the statement
of particulars? He answered that question this way: nothing. He in particular referred to
sections 4 to 7 of the adjudication notice and pointed out that these ran to some 8 pages and
repeated the question what would be the point in setting that out at length in the statement
of particulars. He once more gave the same answer: nothing. The adjudication notice was
produced as part of the documents which accompanied the said letter and 11.3 was
complied with by reference to the content of this notice.
[101] The defender’s point regarding the putting of this information within the statement
of particulars is this: the statement of particulars is the claim to which the defender
responds, it is in a sense the summons to which the defender is required to respond in the
adjudication. It is thus necessary for everything to which it is required to respond to be
within that document. Mr Moynihan submitted, that the above was a misunderstanding, it
is the said notice which is relevant in this context. That is illustrated by the defender’s own
response. It is headed response to the adjudication notice and in the response the
adjudication notice is answered following the numbering system used within the
adjudication notice. The adjudication notice rather than the statement of particulars was the
document which amounted to the summons in terms of the adjudication process.
[102] Mr Moynihan then turned to the statutory framework which is found in section 108
of the 1996 Act. This is an enabling provision telling us what contracts must contain. It sets
out the minimum requirements for an adjudication scheme. If not complied with in a
contract it is the statutory scheme which then is imposed. Here there is a contractual
scheme.
Page 29 ⇓
29
[103] He observed that the statutory scheme did not require a statement of particulars. It
did not require that any particular documents be produced in order to refer the matter to
adjudication. In terms of section 108(2)(a) the notice to refer the dispute to an adjudication
could be as little as a letter. It was simply some form of intimation. The statutory scheme
does not make any reference to how a referral is made. That matter is left to parties. In the
instant case a statement of particulars is just a part of how the matter is referred to
adjudication.
[104] Mr Moynihan said that the only purpose in referring to the statute was this: there
was nothing within it which suggested that a statement of particulars must be
self-contained. There was nothing in the statute to support such a contention. In conclusion
it was his positon that the issue of the giving of particulars should be approached in a
practical manner. Accordingly if by reference to the notice of adjudication all the
information is available to the defender in order to allow them to reply (as they in fact were
able to do) then that was sufficient.
[105] It was his position that there was no merit in this particular point.
[106] In regard to the issue of apparent bias Mr Moynihan set out his positon in four short
propositions:
(a) where a judge or adjudicator made a decision in a related case it does not
necessarily disqualify that judge from hearing a related case raising the same
issue.
(b) the test: is whether there is any reason to doubt the judge will come to the
second case with an open mind.
Page 30 ⇓
30
(c) in the present case there was no reason to doubt that the adjudicator would
come to the adjudication with an open mind as the issues raised before him in
the second adjudication were totally different.
(d) in the second adjudication the adjudicator did at page 3 refer to his first
decision on the nature of what was a defect, but he tells us that because he
has not heard any argument to the contrary he was in a positon to proceed on
the basis of the decision which he had made in the earlier adjudication.
[107] He then turned to look in a little detail at the factual background in the instant case
which gave rise to the issue.
[108] The first adjudication in which the adjudicator sat was between the pursuer and
Amey and related to Stage 1 schools. It was his position that nothing in particular turned on
that matter.
[109] The dispute in that first adjudication arose out of a particular provision in the D&B
contract. The provision in question was a limitation provision relative to latent defects. The
argument in the first adjudication related to this limitation provision. The question of the
proper construction of the word defect arose with respect to the limitation provision. No
engineering evidence was led in that adjudication.
[110] When it came to the second adjudication the subject of the argument before the
adjudicator did not involve Clause 30.5 of the D&B contract (the limitation provision), which
had been the subject of the first adjudication. Limitation was not an issue.
[111] The first issue in the second adjudication was the engineering work: what was the
cause of the collapse? Was there a breach of contract? Secondly, there was an issue
regarding head restraints. Thirdly there was a dispute about how prevalent those defects
Page 31 ⇓
31
were in other Stage 2 schools. Fourthly, there was an issue as to whether it was necessary
for the council to have closed schools rather than have repair work done in the summer.
[112] The adjudicator heard evidence on these issues and came to a conclusion on them.
[113] Given that Clause 30.5 did not feature at all in the second adjudication, the
defender’s argument he submitted is bound to fail.
[114] Although the adjudicator referred to a decision he had made in his first adjudication,
he pointed out that he had not heard any argument on that matter at the second
adjudication and it was not an issue in the second adjudication accordingly there was no
reason for him to, as described by Mr Moynihan, reinvent the wheel. There was no basis to
suggest apparent bias.
[115] Turning to the propositions he had earlier set out there was no basis upon which to
erect an argument of apparent bias. There was no question of the test in Porter v Magill
being satisfied.
[116] As regards the final arguments put forward by Mr Ellis under the broad head of
material breach of natural justice Mr Moynihan’s position was that these arguments were
irrelevant.
[117] The defender’s positon was that it had not been given a fair hearing in that: (1) not
given an opportunity to respond in respect to the title to sue issue; (2) not given an
opportunity to comment on a case relied upon by the adjudicator with respect to title to sue
and (3) the lack of opportunity for the defender to refer to the adjudicator’s decision of 2016.
Mr Moynihan argued that these points were irrelevant in that (1) if the court found in favour
of the defender on the title to sue issue, the action would be dismissed. If, however, the
court took the converse view and repelled the objection of no title to sue then the argument
that there had been a denial of natural justice with respect to the title to sue issue outlined
Page 32 ⇓
32
above is otiose. It does not matter how the adjudicator decided the matter. The matter had
been considered afresh by the court. The hearing before the court supersedes what
happened before the adjudicator. Accordingly there was no merit in this series of
arguments.
[118] For the foregoing reasons Mr Moynihan moved that the court should grant decree
de plano in terms of the first and second conclusions.
Discussion
Title to Sue
[119] The defender’s argument with respect to title to sue can be summarised in this way:
all the pursuer’s rights under the D&B contract have been assigned and accordingly title to
commence proceedings rests with the assignee. I am persuaded that the foregoing is wrong,
in that the pursuer, the cedent is not stripped of title by an assignation in security.
[120] The argument advanced by Mr Ellis I believe is fundamentally flawed. It does not
recognise the fundamental difference between an absolute assignation and an assignation in
security. It is not a matter of dispute that in the instant case the assignation is ex facie and
expressly an assignation in security. It is I believe a well recognised principle that unlike in
the situation of an absolute security the cedent in an assignation in security is not wholly
divested of that which is being assigned.
[121] This difference is recognised in the passages which are set out in full earlier in this
opinion in McBryde, The Law of Contract in Scotland at 12-79, in Maclaren Court of Session
Practice at 219 and Halliday Conveyancing Law and Practice paragraph 8-71.
[122] Each of the above passages recognises that there is a conceptual difference between
an absolute assignation and an assignation in security. Moreover, they recognise that this
Page 33 ⇓
33
conceptual difference has consequences with respect to the issue in the instant case, namely:
the title to sue of the cedent.
[123] The observations made by the first two authors are based upon their consideration of
the same three authorities, namely: Robertson & Co v Exley Dimsdale & Co; Fraser v Duguid;
and Manson v Baillie.
[124] First: Manson v Baillie and others, the material facts are: Manson granted an
assignation in security in favour of Cullen. Cullen raised an action against alleged debtors
of Manson. The court assoilzied the defenders. Cullen declined to proceed any further with
the action. Manson wished to proceed further. The title of Manson to proceed was
challenged.
[125] The Lord President opined in a short judgement as follows at page 777:
“It is very clear that this is a mere assignation in security, by which Manson gave full
power to Cullen to sue this action, on the distinct condition that he should account to
Manson for the whole sums he might recover after satisfying his own debt. Then
Cullen takes up the case, and carries it a certain length, but he declines to incur the
expense of carrying our judgment to appeal. In these circumstances the question is,
whether Manson has an interest to sist himself for the purpose of following out the
appeal? I think he has; for I cannot see why, in this positon of affairs, he should not
proceed himself.”
[126] Lord Mackenzie in an equally short judgment at page 777 said this:
“I think Manson is entitled to be sisted, on the general principle that a party may
always sist himself for his interest. Now, this is not an absolute assignation for a
price paid, in which the cedent’s right is at end; but it is an assignation of security,
containing a direct obligation on the assignee to account to the cedent for any balance
that might remain after his debt was satisfied. It enabled Cullen to sue, not for
himself only, but for Manson also. If he had raised this action for himself alone, the
respondents might be entitled to object to Manson insisting in it at this stage. Cullen
now says that he does not wish to appeal, because his interest is too small to make
that expedient; but Manson thinks differently. The assignation coveys a debt much
larger than Cullen’s claims against Manson; and that being the case, the latter has a
substantial interest to insist in the appeal.”
Page 34 ⇓
34
[127] Lastly Lord Cunninghame at page 778 observed:
“The general rule is, that when the assignee’s right fails, the cedent’s right revives.
Here the right was really Manson’s from the outset; for Cullen was bound to account
to him, if he succeeded, for the whole balance after paying himself.”
[128] Each of the judges appears to me to answer the question before the court regarding
title to sue in favour of the cedent for broadly the same reason, namely: because this was an
assignation in security the cedent’s right was not at an end. Rather the cedent continued in
the circumstances averred to, have retained an interest and therefore had a title to sue.
[129] In Robertson & Co v Exley Dinsdale & Co the facts of the case can be conveniently taken
from the head note: “An assignation of a claim, in security of a debt due to the assignee, and
to the extent of the debt, held (after notice to the assignee who did not object) not to preclude
the cedent for pursing the recovery of the claim so assigned.
[130] The reasoning of the court in holding as above can be seen from the terms of the
interlocutor which was pronounced:
“In respect it is not stated that the pursuers are insolvent, and as the assignation is an
assignation not to the ground of action, but is merely of the balance in security; and
it is admitted that the assignees are responsible to the pursuers for the balance, after
payment of their debt, repels the preliminary defences.”
[131] In the third case of Fraser v Duguid the facts are not material. However,
Lord McKenzie in considering the question of title to sue observed at page 1131 as follows:
“The action is for £1403. The assignation to Johnstone was only for £1102. It did not
divest Fraser in toto, and could not warrant the dismissal of the action in total.”
Again it appears that the decision was based on the cedent retaining an interest.
[132] It appears to me that what can be taken from a proper analysis of these three cases is
the following underlying general principle: that in circumstances such as a partial
assignation or an assignation in security the cedent’s right is not at an end on the assignation
Page 35 ⇓
35
being granted. An assignation either partial or in security does not completely divest the
cedent. It does not divest the cedent for this reason: the cedent may in appropriate
circumstances retain an interest. It follows that the cedent in an assignation in security has
title to sue.
[133] I am satisfied that on a proper analysis of the above cases the defender is wrong in
asserting that these cases do not suggest that as a matter of principle an assignation in
security is to be treated differently as to its effect than an absolute assignation.
[134] A fourth case is relied upon solely by Maclaren as supporting the position he
outlines at page 219. This is the case of McCuaig v McCuaig 1909 SC 355 and it was touched
on briefly in the course of argument before me. In this case the material facts were these: in
a competition between A and B for special service as heir in certain subjects A assigned his
whole interest in the subjects to his law agent. The assignation was ex facie absolute but was
qualified by a back-letter to the effect that it was in security of the agent’s advances and
outlays and that security was limited to £400. The value of the subjects was about £5,000.
[135] The issue in the case was a different one to that which is before me, namely: who
was the dominus litis? The court held that dominus litis was A in that the interest in the cause
remained with him.
[136] The Lord President in his Opinion said this at page 357:
“In the present case I cannot hold that the agent has the true interest in the suit. If
the case is successful, the agent will get at the most, under the assignation, £400,
whereas the appellant will obtain the whole estate – which we are told is, roughly
speaking over £5,000 – minus what is due to the agent. Accordingly the agents
interest seems to me to be merely incidental, and an incidental interest does not
make a party dominus litis even although he may also be supplying the funds
required for the action. The true test of whether a party is or is not dominus litis is
probably whether he has or had not the power to compromise the action. Judged by
that test, I do not think that the agent here can be held to be dominus litis.”
Page 36 ⇓
36
[137] Although the issue before the court was a different one in my view the reasoning of
the Lord President supports the underlying general principle which I have identified.
[138] Applying the above analysis to the circumstances of the case before me I conclude
that the pursuer on a sound reading of the assignation, the CDA and the intimation of the
assignation has an interest of such a type that would bring it within the principle I have
identified as arising from the above authorities.
[139] I would generally observe that from the terms of these documents it is clear that the
pursuer has a significant and continuing interest in the subject matter of the assignation,
namely: the D&B contract. I agree with the argument advanced by Mr Moynihan that it is
not the Security Trustees (the assignees) who have the sole financial interest in the contract.
[140] The above can be seen from the following specific provisions to which I was directed
by Mr Moynihan, namely: the pursuer has a reversionary interest in terms of Clause 16 of
the assignation and a further interest given its present and continuing liability to perform all
of the obligations in terms of the D&B contract and lastly payment by the defenders is
directed to be made to the pursuer’s account.
[141] It is also of some importance to note that any sum recovered by the pursuer from the
defender in respect of the present claim would be payable to the pursuer in terms of
Clause 5.1 and not to the assignees.
[142] It is clear on a sound construction of the assignation, the CDA and the intimation
that unlike in an absolute assignation where the assignee is substituted for the cedent, here
the assignee is not substituted for the cedent, in particular the assignee does not assume any
of the liabilities. Looking to the whole terms of these documents there is a community of
interest between the cedent and the assignee.
Page 37 ⇓
37
[143] Thus given the present and continuing financial interest which the pursuer has it is
given the right and title to sue in respect of that interest. I agree with the argument
advanced by the pursuer that Clause 3.2 of the CDA properly construed means that the
pursuer retains title to sue for its own interest. That is consistent with the terms of
Clause 4.3(b)(iii) of the assignation and Clause 5(d) which allow the assignee to commence
legal proceedings only from the date of the enforcement event as defined in the CDA. Thus
until such an event takes place the pursuer has the interest and has title to sue. After the
enforcement event when the primary interest is that of the assignee, the assignee has title to
sue.
[144] This construction is consistent with the terms of the various documents as a whole
and with the general architecture of these documents and reflects the commercial reality of
the position: that the assignee has no interest until an enforcement event whereas the
pursuer has a highly material interest at least prior to that event. It is not contentious that
no enforcement event has taken place.
[145] What the parties have done here in terms of the whole documentation is to bring
matters within the general principle I have earlier set out. The whole terms of the
documentation and the contractual context favour the position contended for by the pursuer
and its construction of Clause 3.2 of the CDA.
[146] Further and in any event the assignee has given its consent to the pursuer proceeding
with the adjudication. Although it came later on the same day the adjudication notice had
been served that is not relevant. The important point is that as in Manson v Baillie the
assignee did not object when asked about his position.
[147] What I have said regarding the assignation and the pursuer having title to sue in no
way effects (1) the position that there is a valid present assignation of the D&B contract and
Page 38 ⇓
38
(ii) that in a competition between creditors it is as valid and effectual as an absolute
assignation.
[148] Accordingly for the foregoing reasons I am satisfied that the pursuer had title to
bring the adjudication.
The Procedural Argument
[149] I am persuaded that there is no merit in the argument put forward by Mr Ellis.
[150] His primary point is this: the letter relied upon the pursuer to demonstrate the
fulfilment of the obligations incumbent on it in terms of paragraphs 11.2 and 11.3, namely:
the letter of 14 February 2017, does not fulfil these as it does not itself set out the required
details. I can identify no such requirement in the contract. There is no provision in the
contract defining the form in which the information to be contained in the statement of
particulars should be presented.
[151] However, I agree with Mr Moynihan that looking to the terms of 11.3(c)(iv) is
suggestive that all of the information provided does not require to be in the statement of
particulars itself.
[152] It appears to me that as long as the information which is required to be produced in
terms of 11.3 is provided there is no reason that it cannot be supplied by reference in the
statement of particulars to another document. It is in my view sufficient to refer the
recipient by reference to other documents rather than to repeat what may be lengthy
documents ad longum in the statement of particulars itself.
[153] I cannot see any reason why such a reference to another document should not be
sufficient to satisfy the terms of the clause. It was not suggested in the course of the
Page 39 ⇓
39
argument before me that any form of prejudice had resulted to the defender or to anyone
else by this course being followed.
[154] The argument advanced by Mr Ellis that the statement of particulars was equivalent
to a referral notice under the statutory scheme appeared to me to have no real force for the
reasons advanced by Mr Moynihan. The statement of particulars is only one part of the
documentation which in terms of the contractual scheme refers the matter to the adjudicator.
It is noteworthy in this context that it was the notice of adjudication which was responded to
by the defender. The defender did not respond to the statement of particulars. I think that
Mr Ellis was overemphasising the importance of the statement of particulars within the
procedure as set out in the contract. The argument which he advanced did not in my view
support a position that the particulars cannot be provided by reference to documents
outwith the statement of particulars itself.
[155] What in essence we have here is an adjudication notice which contained all the
necessary information for the defender to reply to it, as in fact it did in its response. This
was not a situation where it was unable to reply because of the way in which the particulars
required in terms of Clause 11.3 were presented to it.
[156] I agree with Mr Moynihan that the giving of the information required by Clause 11
should be approached in a practical way. Approaching it in that way I am not persuaded
any proper criticism of the letter relied upon by the pursuer can properly be made. I do not
believe that there is any merit in the argument advanced by Mr Ellis.
Apparent Bias
[157] Turning to the argument in respect of apparent bias the starting point is that when an
Page 40 ⇓
40
adjudicator has made a decision in a case it does not necessarily disqualify him from hearing
a related case raising the same issue.
[158] Thereafter the question is this: whether “a fair minded and informed observer”
would conclude there was “a real possibility for bias”.
[159] It is not a matter of dispute that the substance of the dispute before the adjudicator
in the first adjudication related to a limitation provision and in particular the argument in
terms of the limitation provision turned on the definition of defect for the purposes of that
provision.
[160] Equally it was not disputed that that provision was not an issue in the second
adjudication. It did not feature at all in the second adjudication. Again it was not disputed
that the primary issue in the second adjudication was this: what was the cause of the
collapse of the wall? Flowing from that was the question of whether there had been a breach
of contract? No such points arose in the first adjudication.
[161] There were three further issues in the second adjudication, namely: head restraints;
the prevalence of the defects found in other Stage 2 school and then finally the necessity for
the EDC to close the schools while remedial works were carried out. None of these issues
was before the adjudicator at the first adjudication.
[162] Accordingly the issues before the adjudicator at the first and second adjudications
were entirely different. In no real sense was there any overlap in the issues before the
adjudicator at the first and second adjudications.
[163] The adjudicator did in passing in his second decision refer to his finding with respect
to what amounted to a defect in his first decision. He then said this:
“Given that no contrary argument has been presented on the matter, I see no reason
to depart from my reasoning I deployed in my decision on the Phase 1 dispute for
holding that....”
Page 41 ⇓
41
There is nothing in this passage which could be said to satisfy the test. The adjudicator in
the absence of any contrary argument was clearly entitled to reach this view. Nothing there
could cause a fair minded observer to conclude that there was a real possibility of bias,
[164] It is perhaps interesting to have regard to the factual matrix in Amec Capital Projects
directed by Mr Moynihan) as set out by Dyson LJ at paragraphs 2 – 9 and to note that even
in the extreme circumstances set out there apparent bias was not made out. The
circumstances there amply illustrate that as contended for by Mr Moynihan the present case
comes nowhere near satisfying the test.
[165] For the above reasons I accordingly reject the defender’s argument under this head.
[166] As regards the final matters raised by Mr Ellis in terms of his natural justice
argument I am satisfied that Mr Moynihan’s response, for the reasons he advanced, is
correct. In that I am repelling the argument of no title to sue any denial of breach of natural
justice with respect to that issue is otiose. Thus any failure by the adjudicator to allow the
defender to respond or his reference to a case upon which he was allegedly not expressly
addressed or his alleged failure to allow parties to address him with respect to his first
adjudication decision is irrelevant. The defender has had a full and proper opportunity to
address the court with respect to title to sue and apparent bias. That supersedes what
occurred before the adjudicator. With respect to the decision I have reached I would refer to
the observation of Dyson LJ in Amec Capital Projects v Whitefriar City Estates at paragraph 41.
[167] I accordingly for the above reasons reject Mr Ellis’ argument under this head.
Page 42 ⇓
42
The Third Conclusion
[168] A secondary issue was raised, which related to the third conclusion which sought a
sum said to represent 95% of the expenses of the adjudication. It was argued by Mr Ellis
that this conclusion was irrelevant as the adjudicator’s award made a finding of liability of
expenses but did not finalise the sum due.
[169] Mr Moynihan accepted that the claim was premature: there had been no taxation or
any agreement as to the level of expenses. The claim for practical reasons had not been
taxed or agreed given the substantive disputes regarding the adjudication earlier discussed.
However, it was thought once these issues were decided there could be a further discussion
regarding the expenses issue. It was a more efficient way of dealing with the matters of
expenses to raise it in this action than to have to raise a separate action.
[170] Mr Moynihan’s position was that I should not dismiss the pursuer’s claim in terms of
the third conclusion. Rather if the court were with him regarding the earlier arguments the
matter in terms of conclusion 3 could be continued for taxation or agreement.
[171] Given that the pursuer was not seeking decree in terms of his third conclusion at this
point Mr Ellis was content to leave any further procedure regarding this matter to the court.
[172] Having found in favour of the pursuer with respect to the earlier arguments I believe
it is appropriate to continue the matter in terms of the third conclusion to allow for taxation
or agreement. The practical means by which this can be achieved can be further discussed at
the By Order hearing which I intend to have in this case.
Conclusion
[173] If the court held the adjudication award to be valid, the pursuer, it was accepted by
Mr Ellis, is entitled to decree de plano in terms of his first two conclusions.
Page 43 ⇓
43
Decision
[174] I accordingly sustain the pursuer’s first plea-in-law; repel the defender’s first to
fourth pleas-in-law and award decree in terms of the first two conclusions.
[175] This case will be put out By Order in order that I can be addressed with respect to
how in practical terms I should deal with the issue surrounding the third conclusion and
also with respect to the issue of expenses upon which I have not been addressed.